The Draft Transmission Programmatic Environmental Impact Statement (EIS) was released on March 31, 2025. To review the document visit the Transmission PEIS webpage
There has been an extension to comment on the Draft PEIS until May 15th. 

The Carriger Solar Draft Order #899 is available for comment April 29th through May 1st 11:59 pm. You can see the Draft Order under the "Orders" header towards the bottom of the Carriger Solar webpage.  

There are two Special Meetings for the Carriger Solar project set for May 5th and May 6th. For more information, visit the Carriger Solar webpage

If you would like to submit a comment for either of the above visit our comment database: https://comments.efsec.wa.gov

EFSEC Document

Whistling Ridge Energy Project - Whistling Ridge Energy LLC - Docket:096000

Process Type Document Group(s) Document link File Date Document Set
Adjudication Transcript hearing Volume 7 01/07/2011 02561
Council Transcripts for the Whistling Ridge Wind Energy...
Adjudication Transcript Hearing Volume 8 01/10/2011 02561
Council Transcripts for the Whistling Ridge Wind Energy...
Adjudication Transcript Hearing Volume 9 01/11/2011 02561
Council Transcripts for the Whistling Ridge Wind Energy...
Adjudication Transcript Hearing Volume 10 01/20/2011 02561
Council Transcripts for the Whistling Ridge Wind Energy...
Adjudication Transcript Special Public Meeting 08/03/2011 02561
Council Transcripts for the Whistling Ridge Wind Energy...
Adjudication Transcript Special Council Meeting Workshop Briefing Afternoon Session 10/06/2011 02561
Council Transcripts for the Whistling Ridge Wind Energy...
Adjudication Transcript Special Council Meeting Workshop Briefing Evening Session 10/06/2011 02561
Council Transcripts for the Whistling Ridge Wind Energy...
Adjudication Transcript Special Meeting 12/27/2011 02561
Council Transcripts for the Whistling Ridge Wind Energy...
Adjudication Transcript Wautoma Adjudication Hearing Transcript 09/25/2024 Hearing
Adjudication Transcript Hearing Day 1 08/14/2023 Transcripts
Adjudication Transcript Hearing Day 2 - REDACTED 08/14/2023 Transcripts
Adjudication Transcript Hearing Day 3 08/16/2023 Transcripts
Adjudication Transcript Hearing Day 4 - REDACTED 08/21/2023 Transcripts
Adjudication Transcript Hearing Day 5 - REDACTED 08/22/2023 Transcripts
Adjudication Transcript Hearing Day 6 - REDACTED 08/23/2023 Transcripts
Adjudication Transcript Hearing Day 7 08/24/2023 Transcripts
Adjudication Transcript Hearing Day 8 - REDACTED 08/25/2023 Transcripts
Adjudication Transcript Comment Hearing 08/23/2023 Transcripts
Adjudication Transcript Discovery Conference 07/03/2023 Transcripts
Adjudication Transcript Wautoma Prehearing Conference 1 Transcript 07/22/2024 Transcripts
Adjudication Transcript Wautoma Prehearing Conference 2 Transcript 09/20/2024 Transcripts
Adjudication Transcript Adjudication Public Comment Meeting Transcript 10/03/2024 Transcripts
Application Affidavit Affidavit of Publication/Legal Ad 04/02/2018 00172
Affidavit of Publication of legal ad for Columbia Solar...
Application Agenda Cascade Renewable Pre-App Info Meeting Agenda 02/06/2024 PreAppInfoMtg
Application Agreement Department of Defense (DoD) Agreement 11/10/2020 001
Application Agreement Department of Defense (DoD) Agreement Map 05/03/2021 001
Application Agreement Department of Defense (DoD) Agreement Amended 01/20/2023 001
Application Application Appendix K - REDACTED Biological Reports 02/08/2021 00001
Application Application Revised Application for Site Certification 08/23/2024 00001
Application Application Revised Attachment A - Project Maps 08/23/2024 00001
Application Application Revised Attachment F - Botanical Survey Report 08/23/2024 00001
Application Application Revised Attachment G - Wildlife and Habitat Survey Report 08/23/2024 00001
Application Application Revised Attachment M - Wildlife Habitat Management Plan 08/23/2024 00001
Application Application Revised Attachment O - Acoustic Assessment Report 08/23/2024 00001
Application Application Revised Attachment U - Vegetation and Weed Management Plan 08/23/2024 00001
Application Application Revised Attachment V - Soil Monitoring Memo 08/23/2024 00001
Application Application Cover Letter for Final Application for Site Certification 10/09/2024 00001
Application Application Final Application for Site Certification 10/09/2024 00001
Application Application Final Application for Site Certification Changelog from Revised Version 10/09/2024 00001
Application Application Final Attachment A - Project Maps 10/09/2024 00001
Application Application Final Attachment B - Project Design Schematics 10/09/2024 00001
Application Application Final Attachment C - Legal Descriptions 10/09/2024 00001
Application Application Final Attachment D - Land Use Consistency Review 10/09/2024 00001
Application Application Final Attachment E - Soil Table 10/09/2024 00001
Application Application Final Attachment H - Solar Glare Analysis 10/09/2024 00001
Application Application Final Attachment I - Wetland Delineation Report 10/09/2024 00001
Application Application Final Attachment K - Preliminary Stormwater Management Report 10/09/2024 00001
Application Application Final Attachment J - Preliminary Hydrology Study 10/09/2024 00001
Application Application Final Attachment M - Wildlife Habitat Management Plan 10/09/2024 00001
Application Application Final Attachment N - Socioeconomic Report 10/09/2024 00001