You are here

Home » Energy Facilities » Kittitas Valley Wind Power Project

Kittitas Valley Wind Power Project

Assigned Site Specialist

Sara Randolph
 

Certificate Holder: EDP Renewables North America, LLC
808 Travis Street, Suite 700
Houston, Texas 77002
(713) 265-0350
Proponent: Sagebrush Power Partners LLC
Horizon Wind Energy LLC
53 SW Yamhill St.
Portland, OR 97204
(503)222-9400
Facility: 100.8 MW wind power project
Location: Kittitas County, Washington, 12 miles west of Ellensburg.
Status: Wind power project became fully operational in December 2010.

The Kittitas Valley Wind Power Project is located in unincorporated Kittitas County, Washington, approximately 12 miles west of Ellensburg. The project is located on approximately 5,400 acres of privately and publicly owned forest and rangeland.

The current project consists of 48 wind turbines, a Sagebrush-owned electrical substation, a BPA-owed substation, an operations and maintenance building, and associated supporting infrastructure. EFSEC permitted the project for up to 52 turbines and Sagebrush retains the option to construct four more turbines. The project dispatches electricity through the Bonneville Power Administration transmission system.

Background: In January 2003, Sagebrush Power Partners, LLC, submitted an application for site certification to EFSEC for its Kittitas Valley Wind Power Project. This Project is an alternative energy facility as defined in RCW 80.50.020(17). Sagebrush chose to receive site certification from EFSEC for the Kittitas Valley Wind Power Project pursuant to RCW 80.50.060(2). Application cover letter (1 page - PDF)

On March 27, 2007, EFSEC issued Order No. 826 Findings of Fact, Conclusions of Law, and Order Recommending Approval of Site Certification Agreement. Executive Summary (19kb) Order No. 826 By letter dated June 22, 2007, Governor Gregoire requested EFSEC reconsider the recommended setback for some of the turbines from non-participating landowners' residences.

On August 8, 2007, EFSEC approved Order No. 831 which recommended the Governor approve the Kittitas Valley Wind Power Project with changes to the proposed Site Certification Agreement. These changes would require consideration of visual impacts as the highest priority during the final siting (micro-siting) of the turbines located within 2,500 feet of non-participating residences. Order No. 831, with a revised proposed Site Certification Agreement was delivered to the Governor on August 15, 2007.

On September 18, 2007, Governor Gregoire approved the Kittitas Valley Wind Power Project, and construction began in mid-March 2010. The project became operational in late-autumn 2010. Governor Gregoire's approval letter to the EFSEC Chair.

In November 2008, the Washington Supreme Court upheld the Governor's approval.

General Description of the Project:

The Project will consist of a maximum of sixty-five (65), 3-bladed wind turbines on tubular steel towers, not exceeding a maximum height (hub height plus blade tip height) of 410 feet. The nameplate capacity will be between 98 and 195 megawatts depending on the size of turbine used (1.5 or 3.0 megawatt). The Project would interconnect directly with either Puget Sound Energy's 230kV Rocky Reach-White River transmission line or Bonneville Power Administration's (BPA) Grand Coulee-Olympia or Columbia-Covington 287 kV lines, all of which pass directly over the Project site.

Proposed Site:

The Kittitas Valley Wind Power Project turbines are proposed to be located on the ridges located on either side of Highway 97, roughly halfway between Ellensburg and Cle Elum.

EFSEC's Review Timeline:

May 2009 - Request to Amend the Site Certification Agreement

November 2008 - Washington Supreme Court upholds Governor's decision

February 2008 - Thurston Co. Superior Court transfers case to Washington Supreme Court

October 2007 - Appeal filed in Thurston Co. Superior Court

September 2007 - Governor approves project

August 2007 - EFSEC submits modified recommendation to Governor

June 2007 - Governor remands decision back to EFSEC

May 2007 - EFSEC recommendation delivered to Governor

September 2006 - Hearings held in Kittitas County

May 2006 - August hearings postponed, new hearing schedule to be determined later

March 2006 - Hearings postponed until August 2006

December 2005 - Addendum to Draft EIS issued

August 2004 - Hearings postponed

December 2003 - Draft EIS issued for public comment

May 2003 - Land Use Hearing and 5/7/03 Order on Land Use Consistency

April 2003 - SEPA Scoping Summary issued

March 2003 - Public Informational and Scoping Meeting - Ellensburg, WA

January 2003 - Application for Site Certification submitted to EFSEC

 

Email Updates
To sign up for updates or to access your subscriber preferences, please enter your contact information below.