The Draft Transmission Programmatic Environmental Impact Statement (EIS) was released on March 31, 2025. To review the document visit the Transmission PEIS webpage
There has been an extension to comment on the Draft PEIS until May 15th. 

The Carriger Solar Draft Order #899 is available for comment April 29th through May 1st 11:59 pm. You can see the Draft Order under the "Orders" header towards the bottom of the Carriger Solar webpage.  

There are two Special Meetings for the Carriger Solar project set for May 5th and May 6th. For more information, visit the Carriger Solar webpage

If you would like to submit a comment for either of the above visit our comment database: https://comments.efsec.wa.gov

EFSEC Document Set

Document Search

Carriger Solar -

Compliance

File Datesort descending Document Process Type
02/19/2023 0001-0050 Compliance Comment
02/21/2023 0007 Compliance Comment
02/21/2023 0008 Compliance Comment
02/21/2023 0002 Compliance Comment
02/21/2023 0003 Compliance Comment
02/23/2023 0004 Compliance Comment
02/23/2023 0005 Compliance Comment
02/23/2023 0006 Compliance Comment
02/23/2023 Applicants Informational Meeting Presentation Compliance Presentation
02/23/2023 Applicants Land Use Presentation Compliance Presentation
02/23/2023 EFSEC Presentation Compliance Presentation
02/23/2023 Department of Fish and Wildlife Compliance Comment
02/24/2023 Response to Applicant's Limited Objection to Tri-Cities C.A.R.E.S. Petition to Intervene Adjudication Response
03/01/2023 Tri-Cities C.A.R.E.S. - Notice of Unavailability Adjudication Letter
03/01/2023 Letter to Judge Torem regarding Procedural Considerations Adjudication Letter
03/09/2023 Letter to Judge Torem regarding Input on Issues in Dispute for Adjudication Proceeding Adjudication Letter
03/09/2023 Preliminary Order on Intervention Adjudication Order
03/09/2023 Letter from Yakama Nation and Benton County to Judge Torem regarding Joint Statement of Disputed Issues Adjudication Letter
03/09/2023 Preliminary Order on Intervention Adjudication Letter
03/10/2023 PHC1 Notice Adjudication Notice
03/10/2023 PHC1 Agenda Adjudication Agenda
03/10/2023 PHC1 Transcript Adjudication Meeting Transcripts
03/13/2023 Yakama Nation - Notice of Unavailability Adjudication Letter
03/14/2023 Benton County - Notice of Unavailability Adjudication Letter
03/15/2023 Urtica Fire Control Plan Compliance Plan
03/15/2023 Camas Fire Control Plan Compliance Plan
03/15/2023 Penstemon Fire Control Plan Compliance Plan
03/15/2023 Applicant - Notice of Unavailability Adjudication Letter
03/15/2023 Resolution 299 - Amendment 1 Adjudication Resolutions
03/15/2023 Resolution 332 - Amendment 1 Adjudication Resolutions
03/17/2023 PHC2 Agenda Adjudication Agenda
03/17/2023 Attachment for Pre-Hearing Conference Order #1 Adjudication Documents
03/17/2023 Pre-Hearing Conference Order #1 Adjudication Order
03/20/2023 Yakama Nation Preliminary List of Disputed Issues Adjudication Letter
03/20/2023 Counsel for the Environment Preliminary List of Disputed Issues Adjudication Letter
03/20/2023 Tri-Cities C.A.R.E.S. - Amended Notice of Unavailability Adjudication Letter
03/20/2023 Extension Request Submitted and Withdrawn Compliance Letter
03/20/2023 PHC2 Notice Adjudication Notice
03/20/2023 PHC2 Transcript Adjudication Notice
03/22/2023 Data Request 7 SEPA Letter