You are here

Home » EFSEC Document Set » EFSEC Document Set

The Draft Transmission Programmatic Environmental Impact Statement (EIS) was released on March 31, 2025. To review the document visit the Transmission PEIS webpage
There has been an extension to comment on the Draft PEIS until May 15th. 

The Carriger Solar Draft Order #899 is available for comment April 29th through May 1st 11:59 pm. You can see the Draft Order under the "Orders" header towards the bottom of the Carriger Solar webpage.  

There are two Special Meetings for the Carriger Solar project set for May 5th and May 6th. For more information, visit the Carriger Solar webpage

If you would like to submit a comment for either of the above visit our comment database: https://comments.efsec.wa.gov

EFSEC Document Set

Document Search

Desert Claim - Desert Claim Wind Power LLC

Permits

Information on Kittitas Valley Monitoring reports to Desert Claim as requested from Michael Dunning. (via email)

File Datesort descending Document Process Type
08/23/2013 Avian Monitoring Update 2013 Attachment Permits Report
08/23/2013 Data Summary Attachment Permits Report
09/17/2013 Fall 2012 Post Construction Monitoring Update Permits Report
12/13/2013 EF-131590 Scopng Cmnts 4351-4400 Comment
07/19/2018 Email Cover Permits Email
11/17/2020 November 17, 2020 Meeting Minutes Compliance Transcript