The Grays Harbor Energy Center (Project) consists of two
combustion turbine generators on a "two on one" configuration with
a single steam turbine generator. The Project produces a nominal output
of approximately 530 megawatts, with a maximum output of
approximately 650 megawatts. The
Project is
located on a 20-acre site within
the Satsop Redevelopment Park in Grays Harbor County (location
map). The
entire 20-acre site was previously developed, including grading and surfacing with gravel
and asphalt, and used as an equipment and material laydown area during construction of
WNP-3 and WNP-5.
The Site Certification
Agreement (SCA) for the Satsop Nuclear Project (WNP 3/5) site was
amended in 1996 to allow for construction of a 450 MW gas turbine
project. The
nuclear power projects were removed from the SCA in 1999. In April 2001,
the SCA was amended again to license the current 650 MW gas turbine project.
Construction started on the combustion
turbine project in September 2001, but was suspended in
September 2002
at approximately 56%
completion.
In April
2005, the Site Certification
Agreement was amended
to reflect the sale of the project to Grays Harbor Energy LLC (GHE,
a subsidiary of
Invenergy Inc.) from Duke Energy. Construction was
restarted in February 2007 with commercial operation starting in
April 2008.
On October 30, 2009, GHE submitted a Request for Amendment to the
SCA. GHE requested a 650 megawatt
increase in the facility capacity (to a total
maximum output of approximately 1,300
megawatts), a change the facility name to Grays Harbor Energy Center,
an expansion of the site by 10 acres, approval of a PSD permit for the new units,
and an increase in the total maximum water usage from 9.2 cfs to 16.0 cfs.
For a detailed description of the
amendment process and access to relevant documents, please see the
Request for Amendment webpage.
On December 21, 2010, EFSEC issued Council Order No. 860, recommending that
the governor approve GHE’s amendment request.
The governor approved the amended SCA on February 18, 2011.
| Certificate
Holder: |
Grays Harbor
Energy LLC
PO Box 26
Satsop, WA 98583
(360) 482-4353
|
| Facility
Status: |
|
Phase 1 consists of the existing 650 MW natural gas-fire
combined cycle combustion turbine project and is
operational.
Phase 2 consists of the proposed 650 MW expansion.
Phase 2 has been approved but is not yet constructed.
|
|
|
Status: |
Commercial operation of Phase 1 began April 25, 2008.
|
|
Site Certification
Agreement:
Site Certification Agreement:
PDF
Attachment 1 - Site Legal Description
Attachment 2
- NPDES Permit
Attachment 3 - Water Withdrawal Authorization
Attachment 4 - Mitigation Measures
Attachment 5 - PSD
Units 1&2
PSD/NOC
Units 3&4 PSD/NOC
Project History:
The Council completed its review of the Satsop
Combustion Turbine Project, Application No. 94-1, and the Governor signed the Site
Certification Agreement on May 21, 1996.
In February 2001, the Council authorized
a technical amendment to the Site Certification Agreement, allowing the
addition of Duke Energy Grays Harbor, LLC, as a Site Certification Agreement
co-permittee.
In April 2001, the Council authorized
a technical amendment to the Site Certification, allowing:
-
the replacement of the
originally permitted Westinghouse turbines with General Electric turbines;
-
a modification
of the facility
configuration from a dual "one-on-one" configuration
(two separate but identical combustion turbine generator - steam
turbine generator trains), to a single "two on one"
configuration (two combustion turbine generators - one steam turbine
generator facility);
-
an increase of
the nominal output
of the facility from 490 MW to 530 MW;
-
an increase of the a
maximum output of approximately 650 MW by utilizing duct firing;
-
and removal of the
capability to use diesel oil as a backup fuel.
Construction started on the combustion
turbine project in September 2001 but was suspended in
September of 2002
at approximately 56%
completion.
In April
2005, the Site Certificate was amended
to reflect the transfer of ownership from Duke Energy to Grays Harbor
Energy LLC (a subsidiary of Invenergy Inc.).
Invenergy restarted construction in February 2007.
|
Project Milestones:
October 26, 2012 –
EFSEC Issues Determination of Application Completeness Letter
April 10, 2012 –
GHE Request to Extend Units 3&4 PSD/NOC Permit (in process)
March 9, 2012 - Grays Harbor Energy
NOV Special
Meeting Minutes
March 7, 2012 -
Grays Harbor Energy
Notice
of Special Meeting
February 18, 2011 - Grays Harbor
Energy -
Governor's Approval Letter,
Final Order,
Final SCA
November 10, 2009
-
Request for Expedited
Processing and SEPA Checklist for Amendment No. 5 request.
October 30, 2009 - Request to amend the
SCA to increase capacity by 650 MW by adding new Units 3 & 4, change the name to Grays
Harbor Energy Center, issue a new PSD for Units 3 & 4, and increase
total project water
use.
April 3, 2006
- Final NOC/PSD Permit issued
Final Permit Documents:
Final Permit
March 14, 2006 - Responsiveness Summary
Public
Comment received
March 2005
- Transfer of Ownership to
Invenergy: In early February 2005 EFSEC received a request to
transfer the ownership of the Satsop Combustion Turbine Project.
In March 2005 EFSEC approved the requested
transfer of ownership from Duke Energy Grays Harbor with Invenergy's
finalization of the transactions between Duke Energy Grays Harbor
and Invenergy, and EFSEC's receipt of a financial guarantee of funds
for site restoration.
Links to pertinent documents are listed below:
March 15, 2005
-
Order on Financial Assurances for Site
Restoration
February 25, 2005
-
Order on Application for
Transfer
once certain conditions are met.
February 25, 2005
-
Financial analysis of Invenergy
February 7, 2005
- Determination of Non
Significance regarding Consideration of Request to transfer
ownership of Satsop CT
February 3, 2005
- Duke Energy Request to
transfer ownership of Satsop CT to Invenergy - Public Meeting scheduled for February 23, 2005. |
For information or questions concerning
this project please contact:
Jim LaSpina, EFSEC Specialist
Energy Facility Site
Evaluation Council
1300 S Evergreen Park Dr SW
PO Box 43172
Olympia, WA 98504-3172
(360) 664-1362
To be added to the Satsop
CT Project mailing
list, please:
-
contact Kayce Michelle
Kmichell@utc.wa.gov
at (360) 664-1363,
or
-
e-mail your
complete name and postal address to
efsec@utc.wa.gov
and indicate if you want to receive notices of future permitting
activity for this project by e-mail, surface mail, or both methods of
delivery.
Top of page
|