BP
Cherry Point Cogeneration Project
The BP Cherry Point Cogeneration Project will consist of three natural
gas-fired combustion turbine generators with heat recovery steam
generators, steam turbine generator, and associated equipment, buildings
and structures. The Facility could have a gross nominal generation
capacity of 738 megawatts (MW). Approximately 18 MW will be
consumed on site, and 85 MW would be supplied to the BP West Coast
Products LLC Refinery located near Blaine, Washington (location
map). The Governor approved the BP Cherry
Point Cogeneration Project in December 2004. Development of the
project may be phased with construction of two
(520-570 MW)
of the three combustion turbines during the 1st phase and the
third combustion turbine during the 2nd phase. Construction of the
project has not begun.
|
Site
Certification Agreement
The Site Certification Agreement is the state permit that
lists the conditions that must be met during construction and operation of
the project.
BP Cherry Point Refinery Site Certification Agreement -
Amendment No 1, 10-10-2006 (46 pages)
-
Attachment 1 - Site Legal
Descriptions (1 page)
-
Attachment 2 - Wetland
Mitigation Property Description (1 page)
-
Attachment 3 - Prevention of
Significant Deterioration/ Notice of Construction Permit (13 pages)
-
Attachment 4 - National
Pollutant Discharge Elimination System Permit (29 pages)
-
Attachment 5 - Wastewater
Disposal Permit (18 pages)
-
Attachment 6 - Amended
Stipulation Council for the Environment (13 pages)
-
Attachment 7 - Whatcom
County Settlement Agreement (27 pages)
-
Attachment 8 -
Council Order No. 803 (44 pages)
-
Attachment 9 - Letter of
Understand - Department of Transportation (3 pages)
-
Attachment
10 - Council Resolution No. 317 (9 pages)
Request
for Amendment to Site Certification Agreement 6-20-2006
-
SEPA
DNS - September 11, 2006
PDF (54
pages)
Description of Amendment Request:
PDF (9
pages)
Additional
Information to the Amendment Request 8-10-06
PDF (4
pages)
Redlined SCA.
PDF (47
pages)
SCA Amendment
Cover Letter
PDF (10
pages)
SEPA Checklist
PDF (13
pages)
PSD application 06-20-06
PDF (337
pages).
Appendixes
-
Appendix A
PDF (
3
pages)
-
Appendix B
PDF (
2
pages)
-
Appendix C
PDF (10
pages)
Appendix D
PDF (14
pages)
Appendix E
PDF (12
pages)
Appendix F
PDF (
9
pages)
Appendix G
PDF (16
pages)
Appendix H
PDF (41
pages)
Appendix I
PDF (
1
pages)
Appendix J1
PDF (43
pages)
Appendix J2
PDF (51
pages)
Figures
-
Figure 2-1
PDF (1
page)
-
Figure 2-2
PDF (1
page)
-
Figure 2-3
PDF (1
page)
-
Figure 2-4
PDF (1
page)
Forms
Application Review
2002-2004
Application Review:
SEPA/NEPA
Environmental Impact
Statement,
Adjudicative
Proceedings, Application for Site
Certification,
Other Permits (PSD, NPDES)
For questions concerning the Cherry Point Cogeneration
Project, please contact:
Stephen Posner,
EFSEC Specialist
Energy Facility Site
Evaluation Council
905 Plum Street SE,
3rd Floor
PO Box 43172
Olympia, WA 98504-3172
(360) 956-2063
email:
stephenp@cted.wa.gov
Important Note: Public
comments submitted to the Council via the internet or in writing become
public records under the Washington State Public Records Act (RCW
42.17). Information included in the comment such as the commentor's
e-mail and mailing address becomes a public record once it is provided to
EFSEC and
may be subject to public inspection and copying if not protected by
federal or state law. For additional information please see our Privacy
Notice.
General Information
To be added to the Cherry Point Cogen project mailing
list, please:
- contact Tammy Talburt at (360) 956-2121
or
e-mail your complete name and postal address to
efsec@cted.wa.gov
Top of page
|