Satsop Combustion Turbine Project
SEPA Determination
Request
for Amendment and Expedited Permitting:
Duke Energy notified EFSEC on October 23, 2001 that the current licensed project,
consisting of two
combustion turbine generators on a "two on one" configuration with
a single steam turbine generator, and a 48 mile natural gas
pipeline to supply fuel to the site, is to be considered "Phase
I" pending the submittal of a request to amend the SCA to allow for
the construction of another 650 MW project, consisting of two
combustion turbine generators on a "two on one" configuration with
a single steam turbine generator, called "Phase II".
On November 19, 2001, a request for an amendment to allow for the
construction of Phase II, and for expedited processing pursuant RCW
80.50.075 was received by the Council.
SEPA Determination:
EFSEC has taken lead agency status under WAC 173-11-938 (State
Environmental Policy Act (SEPA) regulations) for the environmental review
of the proposed Phase II project. To assist the Council in making
that determination, Duke Energy provided the Council with an expanded SEPA
checklist.
top
of page
The following are PDF files.
To obtain a free copy of Adobe Acrobat Reader for reading PDF files follow
this link.
Figures, maps, and some tables will
be added to this site as they become available. |
EXPANDED
SEPA CHECKLIST
Environmental
Checklist (49 pages, 326 kB)
A.10
Permits and Approvals (5 pages, 115 kB)
A.11
Site Description (11 pages, 108 kB)
A.12
Project Description (21pages, 144 kB)
B.2
Air Quality Analysis (26 pages, 284 kB)
B.3
Water Resources Report (44 pages, 262 kB)
B.5
Fish and Wildlife Report (22 pages, 235 kB)
B.7
Noise Report (20 pages, 177 kB)
B.10
Visual Resources Report (26 pages, 171 kB)