The Desert Claim Wind Power Project is a 180 megawatt (MW) wind power project located on approximately 4,783 contiguous acres in Kittitas County, eight miles northwest of Ellensburg, Washington (location map).  The Project consists of a maximum of 90 turbines and associated electrical collection system that would connect the Project to the regional high-voltage transmission grid.  The Project area includes land leased from private and public land owners.   

The Desert Claim Wind Power Project will use REpower MM92 model turbines.  This turbine model has a tower height of 262.5 feet, a rotor diameter of 303 feet with a total height of 414 feet.  Each turbine has a nameplate generating capacity of 2.0 MW.

The Application for Site Certification was submitted on November 6, 2006.  EFSEC's review is ongoing.

Applicant: Desert Claim Wind Power LLC
PO Box 4
Woodinville, WA 98072
425-941-3774

 
Facility: 180 MW Wind Power Project
 
Location: Kittitas County  project map
 
Status: Application for Site Certification submitted on November 3, 2006 is under review. 
 
General Information:

Application for Site Certification:

Introduction Cover, Submittal letter, Table of Contents (1,593 KB)
Project Project Description (2,891 KB)
Figures Project Figures (7,854 KB)
Tab 2 Visual Simulations (15,309 KB)
Tab 3 Regulatory Matrix (152 KB)
Tab 4 Wetland Information (848 KB)
Tab 5 Update on Vegetation & Wildlife Impacts (3,025 KB)
Tab 6 Sound Mapping (2,535 KB)
Tab 7 Hazard Zones (324 KB)
Tab 8 Shadow Mapping (6,230 KB)
Tab 9 Lighting (1,118 KB)
Tab 10 Supplemental Regulatory Information (1,193 KB)
FEIS Final Environmental Impact Statement

Land Use Consistency:

Council Order No. 825 - Land Use Consistency
Land Use Consistency Hearing Transcript

Recent Activity:

2/12/08 EFSEC approves Desert Claim's request to extend application review time.

6-29-07 Request for Preemption - enXco's request for preemption.  Declaration of David Steeb.

5-8-07 Council Order No. 830 - Order on Determination that Desert Claim Wind Power has Satisfied WAC 463-28-030(1)

 5-1-07 Council Order No. 829  - Request for Extension to File Request for Preemption

4-26-07 SPECIAL MEETING April 30, 2007 Request to Extend 90 Day Time Limit.

   MEETING DOCUMENTS:
enXco's Motion - WAC 463-28-030(1) Satisfied;
Mr. Steeb's Declaration Support of Motion; EFSEC requests Response from Recipients
Kittitas County's Response to Motion; Commissioner Crankovich Affidavit,
Mr. Piercy's Affidavit;
enXco's Supplemental Briefing,
enXco's Request for Extension.

  Golder Report (PDF format) - Analysis in
Support of a SEPA Threshold Determination
for the Desert Claim Wind Power Project - February 2007
   

 

Top of page

Project Mailing List

To be added to the Desert Claim project mailing list, please:

  • contact Tammy Talburt at (360) 956-2121
    or
  • e-mail your complete name and postal address to efsec@cted.wa.gov  (Please indicate whether you wish to receive Desert Claim project information and meeting notices by email or U.S. Mail)

Page modified 9-7-07

Top of page


Home Page | About EFSEC | Certification | Energy Facilities 
Laws & Rules
|
Rulemaking | Meetings | Staff Contacts  
Site Map | Links | Privacy Notice   

Washington State Community, trade and Economic Development Logo Department of Community, Trade and Economic Development  

Access Washington Logo   Access Washington

www.efsec.wa.gov
Question or Comment? Contact EFSEC at efsec@cted.wa.gov